Copper Project · Katanga Province, DRC

80 km of HDPE pipe supplied into Central Africa.

A large-scale supply programme delivered in coordination with SENET for a copper project in the DRC.

ClientLarge DRC copper producer / SENET.
ScopeSupply of HDPE pipe and associated fittings.
Scale80 km of HDPE pipe and 2,830 fabricated fittings.
Logistics340 trucks dispatched.
QualityDaily inspections by SENET over a six-month period.

Figures above come from Sinvac's published DRC project case study.

Zinc Concentrator · Gamsberg Mine

17 km of in-plant HDPE piping delivered incident-free.

A complex concentrator scope combining HDPE, lined carbon-steel pipe, flexible hose, valves and steel supports.

HDPE17 km of pipe and approximately 17,500 HDPE fittings.
Additional scope2.5 km lined carbon-steel pipe, more than 1 km flexible hose, 1,116 valves and 5.6 tonnes steel pipe supports.
Team86 Sinvac project team members.
Duration10 months.
OutcomeConstruction, commissioning, completion and handover completed with zero incidents stated in the case study.

Project quantities and safety outcome are taken from Sinvac's published Gamsberg material.

Overland Piping · Basil Read Matomo Projects

14 km installed in a 19-week delivery period.

A dedicated Sinvac team manufactured, supplied, fabricated and installed the overland HDPE system.

Scope14 km of overland HDPE pipe and associated fittings.
IncludedValves, special in-line items, plinths and thrust blocks.
TestingPressure testing completed to check conformance to project requirements.
Duration19 weeks total project delivery.

Scope and delivery period are from Sinvac's published Overland Piping case study.

Chrome Tailings Retreatment Plant · Rustenburg

More than 4 km of mixed piping and fittings in 12 weeks.

A plant-piping package delivered for Basil Read Matomo Projects.

ScopeMore than 4 km of HDPE, CS, GCS and RRPVC piping plus associated fittings.
IncludedValves, special in-line items and steel pipe-support fabrication and installation.
TestingPressure testing and commissioning assistance.
Duration12-week project delivery period.

Scope and timing come from Sinvac's published Chrome Tailings Retreatment Plant case study.

From evidence to enquiry

Have a similar pipeline scope?

Send the length, pipe diameter, pressure class, application, location and available drawings so the technical team can understand the scale immediately.

Submit a project brief ↗
In-plantFabrication + installation
OverlandLong-distance HDPE systems
MiningProcess / slurry / water
Close-outPressure test + sign-off support